CASE STUDY
Reducing SAP Infrastructure Costs While Ensuring Resilience
SAP ECC and BW/4HANA cloud migration
A US telecom provider needed to modernize its SAP landscape, ensure disaster recovery, and cut infrastructure costs without disrupting operations.
Technical Path
Executed staged migration with HANA replication for BW/4HANA HADR, Sybase DR via backup/restore, sandbox testing for SP upgrade, and full AWS re-platforming.
CASE STUDY
Modernizing ERP for Cost Savings and Mobile Access
SAP cloud migration and ERP modernization
To reduce costs and enable mobile access, a top consumer goods distributor needed to migrate their ERP from ECC to S/4HANA 2020 via RISE with SAP on Azure.
Technical Path
Converted ECC (EHP6/MSSQL) to S/4HANA 2020 via RISE, deployed 3-tier Azure landscape, enabled Fiori UX, used SAP tools for planning and readiness.
CASE STUDY
Unifying SAP Operations Across 40 Subsidiaries
SAP domain migration and infrastructure modernization
A 40-company multinational needed to unify SAP operations and ensure S/4HANA readiness—without business disruption.
Technical Path
Migrated 37 SAP systems (ECC, CRM, BW, PO, SolMan, BOBJ) to a unified Windows domain; maintained high availability; validated integration across SAP and non-SAP systems.
CASE STUDY
Upgrading SAP for DR and S/4HANA
SAP upgrade, DR setup and modernization support
A major seismic data company wanted to improve SAP performance, ensure disaster recovery, and be ready for S/4HANA.
Technical Path
Performed EHP and database upgrades; set up SSO, FIORI, EP, and ADS; refreshed infrastructure; built cloud DR; enabled VAT; ran S/4HANA readiness check.
CASE STUDY
Scaling for Global Growth with S/4HANA
PCE migration for global growth and security
A multinational enterprise required the modernization and alignment of four ECC systems on S/4HANA Private Cloud Edition to strengthen security, streamline integrations, and support global scalability.
Technical Path
Migration readiness and sandbox testing; security role realignment and Fiori enablement; integration validation; delivered in 14 months with minimal disruption.